Christie's finished ADU in Chino, CA

Christie's Estate 950 ADU in Chino, CA

We really made an excellent choice when we chose Backyard Estates.

Watch their 4-minute story

Creating a comfortable multigenerational living space to support their daughter, grandchildren, and future family needs.

At first, I honestly thought the idea of building an ADU in our backyard was a little crazy. We had explored buying a separate home for our daughter and her five children, but the cost of purchasing another property was overwhelming. At the same time, having everyone under one roof was becoming difficult, and we knew we needed a better solution.

How can we support our daughter and grandkids while still giving everyone their own space?

That’s when we started asking ourselves: How can we support our daughter and grandkids while still giving everyone their own space?

Inside Christie's ADU
Inside Christie's ADU

We initially looked into working directly with the City of Chino and their preapproved ADU plans, but it quickly became confusing. One person would tell us one thing, and someone else would completely contradict it. That’s when we found a Backyard Estates open house on Facebook.

Adam and Tom made us feel comfortable. They wanted to know our story and genuinely seemed to care about helping people.

Walking into the open house changed everything. We were immediately impressed with the quality—especially the cabinetry and finishes. But more than that, Adam and Tom made us feel comfortable. They wanted to know our story and genuinely seemed to care about helping people. That personal connection made a stressful situation suddenly feel possible.

Christie's ADU in Chino, CA

The moment they broke ground, we realized how organized and efficient Backyard Estates really was. We were told that within seven weeks the ADU would already be standing—and they were right. Watching multiple trades work seamlessly together felt like watching one of those home renovation shows. It was amazing seeing how fast everything came together.

It was amazing seeing how fast everything came together.

One thing that meant a lot to us was the professionalism of everyone on site. There wasn’t a single contractor or tradesperson that stepped on this property that we didn’t feel good about. That level of trust was huge for us based on past experiences.

There wasn’t a single contractor or tradesperson that stepped on this property that we didn’t feel good about.

Play from 1:58Christie, in their video

Designing the interior became one of my favorite parts of the process. We absolutely loved selecting the cabinetry and adding our own personal touches—especially the avocado green island that gave the home warmth and personality. It was awesome being able to put together kind of a dream.

It was awesome being able to put together kind of a dream.

Christie, at 2:49 in their video

Most importantly, this ADU allows our family to stay close. We can help support our daughter and grandchildren now, and one day they’ll be there to support us as we age. That peace of mind means everything.

Without hesitation, we really felt like we had made an excellent choice when we chose Backyard Estates.

The home they built

La Causey’s custom floor plan
Size
947 sq ft
Rooms
2 bedrooms, 2 baths
Type
Detached, in the backyard
  • Luxury Vinyl Plank - Malibu
    FlooringMalibu
  • Shaker Cabinets - White Oak
    CabinetsWhite Oak
  • Shaker Cabinets - Olive Green
    CabinetsOlive Green
  • Countertop - Misterio Gold
    CountertopsMisterio Gold
  • Wall Tile - Bright Gold
    Shower tileBright Gold
  • Cabinet Pulls - Matte Black
    HardwareMatte Black

From first sketch to move-in day

Their real dates, from the first design meeting to the final inspection.

DesignJun 24 to Sep 25
13 weeks
City permitsSep 25 to Jan 19
17 weeks
ConstructionJanuary to March
8 weeks

City permits in Chino

Christie
Chino average

16 weeks faster than the 33-week average

Construction

Christie
Chino average

22 weeks faster than the 30-week average

The eight weeks of building

  1. Week 1: site prep and groundwork
    Week 1Site prep and groundwork
  2. Week 2: foundation and footings
    Week 2Foundation and footings
  3. Week 3: framing and rough-ins
    Week 3Framing and rough-ins
  4. Week 4: windows, doors and exterior shell
    Week 4Windows, doors and exterior shell
  5. Week 5: insulation and drywall
    Week 5Insulation and drywall
  6. Week 6: interior and exterior finish
    Week 6Interior and exterior finish
  7. Week 7: cabinets and countertops
    Week 7Cabinets and countertops
  8. Week 8: interior touch-ups and final inspection
    Week 8Interior touch-ups and final inspection

Start where they started. A visit to our office.

See floor plans, finishes and what fits your lot, with the team that built Christie's home.

Book your free office visit

Or call or text (909) 500-0917

More stories in their own words