Richard's finished ADU in La Verne, CA

Richard's Estate 750 ADU in La Verne, CA

I would without hesitation recommend Backyard Estates because of the quality of the construction and the design.

Watch their 4-minute story

Giving his son Tony a home of his own on the family property, so Richard can finally travel with peace of mind.

My name is Rich Losee, and I decided to build the ADU to give my son a place to live. He's not at this point able to afford rent. We visited apartments to see what kind of cost would be associated with renting one, and it was just way too much. So we started investigating ADUs.

We talked to one or two other ADU builders. Then I was at an intersection near your offices in Upland, and I saw a truck going through the intersection in front of me that said Backyard Estates. I said, well, I need to talk to those guys. So I called and got a very good feeling talking to Adam and Tom Gibson. They seemed concerned about what our issues were and what it is that we were trying to accomplish.

They seemed concerned about what our issues were and what it is that we were trying to accomplish.

We have a tree in the yard that we wanted to preserve. If we had put just a rectangular structure in there, it would have taken the tree out. But by customizing the design a little bit, the architect was able to make a space for that tree. The house just blends right in. Actually, that's pretty incredible. If we had gone with a pre-manufactured unit, the tree would have gone.

By customizing the design a little bit, the architect was able to make a space for that tree.

What was most impressive was the construction, led by Dusty. He was on top of everything. He came through, checked on the site and had his checklist. The crew who did the foundation was really, really good, and it was neat to see these guys working. They worked together, they knew what they were doing, and they worked as a team. That was very cool. The guy who did the stucco did a great job, and his team did a really nice job.

Inside Richard's ADU
Inside Richard's ADU

It's really been, to my surprise, an incredible experience. From ground break to now, it's been about nine and a half weeks, so it was done in nine weeks or so. That's pretty fabulous, and it's so well done.

It was done in nine weeks or so. That's pretty fabulous, and it's so well done.

There was still a significant amount of anxiety associated with it. Part of that is just that it's such a big task, a big job to do, and the other part is that it costs a lot of money. I feel like it was well spent in this case. When it was finished, I slept for a whole day afterwards. It was just a relief.

Richard's ADU in La Verne, CA

The way I expect to benefit most is the ability to travel. With this house, Tony will have his own space that he'll be responsible for. Now that it's completed, I can walk away for a week or a month at a time, and I'm looking forward to that.

Now that it's completed, I can walk away for a week or a month at a time, and I'm looking forward to that.

I would without hesitation recommend Backyard Estates because of the quality of the construction and the design, but also the sense of satisfaction and mental ease that I had working with Backyard.

The home they built

Cadley’s custom floor plan
Size
749 sq ft
Rooms
2 bedrooms, 1 bath
Type
Detached, in the backyard

From first sketch to move-in day

Their real dates, from the first design meeting to the final inspection.

DesignApr 3 to Jun 16
11 weeks
City permitsJun 16 to Aug 17
9 weeks
ConstructionAugust to November
11 weeks

City permits in La Verne

Richard
La Verne average

11 weeks faster than the 20-week average

Construction

Richard
La Verne average

11 weeks faster than the 22-week average

The eleven weeks of building

  1. Week 1: site prep and groundwork
    Week 1Site prep and groundwork
  2. Week 2: foundation and footings
    Week 2Foundation and footings
  3. Week 3: framing and rough-ins
    Week 3Framing and rough-ins
  4. Week 4: windows, doors and exterior shell
    Week 4Windows, doors and exterior shell
  5. Week 5: insulation and drywall
    Week 5Insulation and drywall
  6. Week 6: interior finish
    Week 6Interior finish
  7. Week 7: exterior finish
    Week 7Exterior finish
  8. Week 8: cabinets
    Week 8Cabinets
  9. Week 9: countertops
    Week 9Countertops
  10. Week 10: interior touch-ups
    Week 10Interior touch-ups
  11. Week 11: final inspection
    Week 11Final inspection

Start where they started. A visit to our office.

See floor plans, finishes and what fits your lot, with the team that built Richard's home.

Book your free office visit

Or call or text (909) 500-0917

More stories in their own words