ADU DesignArchitectural PlansStructural EngineeringTitle 24Civil EngineeringPlan Check FeesBuilding & Fire FeesWater & City FeesNotarizationCounty RecordingAgency CoordinationZoning VerificationProject ManagementCity InspectionsCertificate of OccupancyTurn-Key ConstructionPremium FinishesUtility ConnectionsWeekly UpdatesFinancingExterior DesignInterior DesignPre-ConstructionFinal WalkthroughWarranty SupportADU DesignArchitectural PlansStructural EngineeringTitle 24Civil EngineeringPlan Check FeesBuilding & Fire FeesWater & City FeesNotarizationCounty RecordingAgency CoordinationZoning VerificationProject ManagementCity InspectionsCertificate of OccupancyTurn-Key ConstructionPremium FinishesUtility ConnectionsWeekly UpdatesFinancingExterior DesignInterior DesignPre-ConstructionFinal WalkthroughWarranty Support

Designed to feel like home.

Myrtus started as our Estate 750 and was customized for this home.

Project Timeline Overview

0 weeks

Plans

0 weeks

Permits

0 weeks

Construction
Week 1
Site Prep & Groundwork
Site Prep & Groundwork
Week 2
Footings
Footings
Week 3
Concrete Pour
Concrete Pour
Week 4
Framing & Rough-Ins
Framing & Rough-Ins
Week 5
Windows, Doors & Exterior Shell
Windows, Doors & Exterior Shell
Week 6
Insulation
Insulation
Week 7
Exterior Scratch & Stucco
Exterior Scratch & Stucco
Week 8
Drywall
Drywall
Week 9
Interior Finishes
Interior Finishes
Week 10
Cabinets & Countertops
Cabinets & Countertops
Week 11
Exterior Touch-Ups
Exterior Touch-Ups
Week 12
Final Inspection
Final Inspection

Site work on this lot

No surprises. Here’s why.

Our Formal Property Analysis found all of this before they signed.

Step 1 of 2

Found before we started

Our architect and engineers checked this lot before we designed anything. Finding these early is how we avoid surprises during the build.

Longer utility runs (140 feet): The utility trench, May 12, 2026

The utility trench, May 12, 2026

Longer utility runs (140 feet)

What we found during the FPA
Sewer, water and power lines had to run farther than usual.
How finding it early helped
We mapped the route and checked the sewer’s slope over that distance, then sized the pipe and wire for the length.
What it meant for this homeowner
The yard was dug once, and every line works the way it was planned.
Fire sprinklers: Sprinkler lines in another ADU we built

Sprinkler lines in another ADU we built

Fire sprinklers

What we found during the FPA
The fire department required sprinklers in the ADU.
How finding it early helped
Planning sprinklers from day one meant the water line, meter and ceilings were sized for them, and the fire department reviewed one complete design.
What it meant for this homeowner
No redesign after approval, and sprinklers that fit cleanly into the finished rooms.
Fire flow test: A fire hydrant at one of our jobs

A fire hydrant at one of our jobs

Fire flow test

What we found during the FPA
The fire department needed a flow test of the nearest hydrant.
How finding it early helped
The result tells us right away if the fire department will require sprinklers, which changes the water line, the ceilings and the permit. So all of it was settled before the design.
What it meant for this homeowner
Plans that met the fire department’s rules from day one, with no late redesign.
Water meter upgrade: At the FPA site visit, Jul 31, 2025

At the FPA site visit, Jul 31, 2025

Water meter upgrade

What we found during the FPA
The water meter was too small to serve two homes.
How finding it early helped
Sizing the new meter at the start let the water district swap it while the ADU was still being built.
What it meant for this homeowner
Good water pressure in both homes, with no wait on the water district at move-in.
Electrical load calculations: At the FPA site visit, Jul 31, 2025

At the FPA site visit, Jul 31, 2025

Electrical load calculations

What we found during the FPA
The electrical panel had to power two homes.
How finding it early helped
Our load calculation showed what the panel could carry, so any upgrade and the utility’s scheduling started early, not after the walls went up.
What it meant for this homeowner
Power for both homes from day one, with no wait on the utility.
Over-excavation under the foundation: Digging out the pad, May 12, 2026

Digging out the pad, May 12, 2026

Over-excavation under the foundation

What we found during the FPA
The soil under the ADU had to be dug out and packed down again before the foundation.
How finding it early helped
The soil findings set how deep to dig and how tight to pack it, so the dig, the compaction tests and the foundation were all in the plan from the start.
What it meant for this homeowner
A solid base under the home, with no stop for soil work in the middle of the build.
  • Concrete cut and poured back (60 sq ft): Pouring the new concrete, Jul 2, 2026

    Pouring the new concrete, Jul 2, 2026

    Concrete cut and poured back (60 sq ft)

    Concrete cut for the trench, then poured back.

  • Small tree removed: Removing a tree at one of our jobs

    Removing a tree at one of our jobs

    Small tree removed

    Trees and old yard items cleared for the ADU.

City permits and fees

Already included in every price, in every city we build in.

StepWho we work withFees we pay
Plan reviewPlanning, Building, Engineering, City / County Fire, CA ADU LawPlan-check, fire, corrections review, state compliance
UtilitiesPublic Works, Water, Electric Provider, WasteWater, sewer and electric connection and capacity
PermitSchool Districts, RecorderSchool, address, notarization, building, permit pull
InspectionsBuildingInspection

Added for this lot

  • Encroachment permitA city permit to work in the street or sidewalk to reach the utilities.

Step 2 of 2

Finished to match the house

So the ADU looks like it belongs with the house.

The finished ADU
  • GuttersGutters that keep rainwater away from both homes.

Our team

Your team, from first visit to move-in.

One team. Every step.

  1. Plan

    • Serge MayerHead ArchitectWalks your lot and draws your plans. Civil engineering and surveying background.
  2. Permits

    • Mary CoonDirector of OperationsKeeps every step moving: permits, schedule, people.
    • Elsa TomasProject AdminYour updates and documents, in one place.
  3. Build

    • Tom GibsonDirector of Construction50+ years building. Sets how every ADU gets built.
    • Dusty GravattSenior Construction Mgr.Runs the job site and the crews.
    • Jose CervantesProject ManagerRuns your schedule from permit to move-in.
  4. Every step

    • Adam StewartPresident & FounderStands behind every build.
    • Edgar CureMarketing & Tech Mgr.Builds the tools that show you every number.

Formal Property Analysis (FPA)

Your lot has its own requirements. Find them before you build.

For Myrtus, our architect and engineers checked 250+ things before anything was designed.

Myrtus’s FPA250+ checks
  • Soil and foundationSoil dug out and recompactedFound
  • Utility run lengthsRouted and sized before any diggingFound
  • Water meter sizeA bigger meter, set during the buildFound
  • Electrical panel sizePower for both homes, planned earlyFound
  • Fire department rulesFire rules met in the first designFound

Also checked

  • Zoning and setbacks
  • Height and size limits
  • Slope and drainage
  • Sewer line condition

And 240+ more on every lot

  • What your lot needs
  • A buildable solution
  • A proposal with no surprises
Book your FPA

$500, fully credited toward your build

Not ready? Start with a free office visit

Finishes in this home

Designed with purpose, finished with care.

Every finish and fixture is selected with intention.

  • Luxury Vinyl Plank - Oyster

    Flooring

    Oyster

  • Shaker Cabinets - Misty Gray

    Cabinets

    Misty Gray

  • Shaker Cabinets - White

    Cabinets

    White

  • Countertop - Calacatas Vega

    Countertops

    Calacatas Vega

  • Cabinet Pulls - Matte Black

    Hardware

    Matte Black

  • Kitchen Faucet - Matte Black

    Kitchen faucet

    Matte Black